#11
Kembangan Station has its PSD fully fitted with TO doors,awaiting to be operational
Commonwealth Station going to have TO doors installed most likely to be fully fitted by next week
Reply
#12
Expect KAL PSD to operate this week
Reply
#13
TO doors at COM commenced installation today, with the 'skeleton' of the structure seen going up at TW of WB side.
Teo Wei Shen
Member, Projects & Support Dept.

Website | Facebook | Twitter | Google Plus
Reply
#14
TO doors already installed at TNM.
Reply
#15
Urgh...east side left with Simei and Tampines Sad
Reply
#16
(21 February 2011, 09:35 PM)jcqh Wrote:   Show/Hide

Expo as well Thumbs Up
Reply
#17
(21 February 2011, 09:34 PM)Kawasaki C151 Wrote:   Show/Hide

so fast................Confused
Reply
#18
UPDATES ARE ALSO AVAILABLE ON FACEBOOK! YOU MAY CHOOSE TO POST IN THESE SITES ALTERNATIVELY.
East West Line
North South Line

Information is available in the HHPSD tab.

6. FULLY OPERATIONAL (14/37)
1. PSR - 54 (LIVE as of 01/11/09)
2. YIS - 54 (LIVE as of 02/12/09)
3. JUR - 108 (LIVE as of 18/12/09)
4. CLE - 54 (LIVE as of 16/08/10)
5. BGB - 54 (LIVE as of 16/08/10)
6. LKS - 54 (LIVE as of 31/08/10)
7. BBT - 54 (LIVE as of 31/08/10)
8. CNG - 54 (LIVE as of 01/10/10)
9. EUN - 54 (LIVE as of 12/16/10)
10. BDK - 54 (LIVE as of 11/01/11)
11. PYL - 54 (LIVE as of 11/01/11)
12. ALJ - 54 (LIVE as of 11/02/11)
13. KEM - 54 (LIVE as of 25/02/11)
14. KAL - 54 (LIVE as of 25/02/11)

5. FULLY FITTED, AWAITING OPERATION:
EW4 Tanah Merah
NS1/EW24 Jurong East Platform E/F

4. UNDER RETROFITTING:
EW20 Commonwealth
EW19 Queenstown

3. BLACK-YELLOW PANELS:
EW18 Redhill
EW21 Buona Vista

2. RECTANGULAR SKETCHES:

1. REINFORCED RED MARKINGS:
EW3 Simei
EW22 Dover
EW27 Boon Lay

STATIONS CURRENTLY WITHOUT ANY SIGNS OF FITTING
EW2 Tampines
EW3 Simei
EW28 Pioneer
EW29 Joo Koon
CG1 Expo
NS4 Choa Chu Kang
NS5 Yew Tee
NS7 Kranji
NS8 Marsiling
NS9 Woodlands
NS10 Admiralty
NS11 Sembawang
NS14 Khatib
NS15 Yio Chu Kang
NS16 Ang Mo Kio

Total of 27 sets per platform out of 38 ELEVATED Stations.
20/38 stations without HHPSD.
Reply
#19
kembangan and kallang psd in operation

*info from SBS8888D
My Darling is a fishball and its tail is too powderful Tongue

Heart 47/48
Reply
#20
commonwealth psd havn't operate yet
Reply


Possibly Related Threads...
Thread Author Replies Views Last Post
  Retrofitting of Fixed Barriers at LRT Stations gs97 65 35,922 24 May 2018, 09:07 AM
Last Post: A380Lover

Forum Jump:


Users browsing this thread: 2 Guest(s)