[Press Release] LTA Awards Final Construction Contract for Circle Line 6
#1
LTA Awards Final Construction Contract for Circle Line 6
Press Release 10/11/17

1. The Land Transport Authority (LTA) has awarded the final civil contract for Circle Line 6 (CCL6) for the construction of Cantonment Station to China State Construction Engineering Corporation Limited (Singapore Branch) at a contract sum of S$205 million.

Scope of Contract

2     The construction of the three-level underground station along Keppel Road will commence by end-2017 and be completed in 2025. Cantonment Station will be built with a Civil Defence shelter, the 12th Civil Defence shelter on the Circle Line (CCL).

3     China State Construction Engineering Corporation Limited (Singapore Branch) is an established contractor which has completed many railway infrastructure projects in Singapore and China. They most recently completed the construction of Downtown Line 3’s Kaki Bukit and Geylang Bahru Stations, and are currently involved in the design and construction of North-South Line’s Canberra Station. They are also in a joint venture with Nishimatsu Construction Co. Ltd to construct the CCL6 Keppel Station and tunnels.

Read More
Reply


Possibly Related Threads...
Thread Author Replies Views Last Post
  Possible New MRT Line emoh 3 837 12 June 2019, 08:31 PM
Last Post: emoh
  [Press Release] New Addition to North-South Line: Canberra Station A380Lover 2 1,796 29 May 2019, 07:01 PM
Last Post: C151andC651SuperAUTTP
  [News Article] North-East Line, Sengkang and Punggol LRTs to move to new financing framework A380Lover 0 14,041 14 February 2018, 07:55 PM
Last Post: A380Lover
  [Press Release] Factsheet: Status of Construction of the Thomson-East Coast Line A380Lover 0 7,504 10 November 2017, 04:33 PM
Last Post: A380Lover
  [News Article] Thomson-East Coast Line could be extended to connect to Changi Airport A380Lover 7 5,335 29 April 2017, 09:49 AM
Last Post: xavier2002
  [News Article] Faults affect Circle Line due to "intermittent signalling issues" A380Lover 3 2,336 26 November 2016, 01:38 PM
Last Post: A380Lover
  [Press Release] Limited Tender for Thomson-East Coast Line Operator Licence in 1Q2017 A380Lover 0 1,465 05 November 2016, 11:27 AM
Last Post: A380Lover
  [Press Release] The Rail Report: New Signalling System, Rail Line and Extension and Trains Next Year A380Lover 0 1,108 26 October 2016, 07:40 PM
Last Post: A380Lover
  [News Article] Dislodged platform door causes disruption on Downtown Line A380Lover 0 1,043 07 October 2016, 09:17 AM
Last Post: A380Lover
  [News Article] Faster rides on East-West Line by year end A380Lover 0 1,385 28 August 2016, 05:14 PM
Last Post: A380Lover