[Press Release] Completion of Sleeper Replacement Programme on the North-South and East-West Lines
#1
Completion of Sleeper Replacement Programme on the North-South and East-West Lines
Press Release 20/01/17

1. Coordinating Minister for Infrastructure and Minister for Transport, Mr Khaw Boon Wan, officiated the completion of the sleeper replacement programme on the North-South and East-West Lines (NSEWL) today. This marks a significant milestone of a four-year effort to improve commuter experience on the 29-year-old NSEWL, Singapore’s oldest and most heavily-utilised rail lines.

2. The 188,000 wooden sleepers have been in use since the NSEWL started operations close to thirty years ago, and were nearing the end of their useful life. In August 2013, LTA and SMRT embarked on a multi-year project to replace these ageing wooden sleepers with concrete sleepers, along all 200km of tracks on the NSEWL. Besides being more durable, the completion of the sleeper replacement will also improve journey times and provide commuters a smoother ride.

3. A commemorative plaque, signed by Minister Khaw, will be installed at Clementi MRT Station, where the last batch of wooden sleepers were replaced with concrete sleepers on the westbound track on 20 December 2016.

[Read More]
Reply


Possibly Related Threads...
Thread Author Replies Views Last Post
  [Press Release] New Addition to North-South Line: Canberra Station A380Lover 2 1,859 29 May 2019, 07:01 PM
Last Post: C151andC651SuperAUTTP
  [News Article] North-East Line, Sengkang and Punggol LRTs to move to new financing framework A380Lover 0 14,177 14 February 2018, 07:55 PM
Last Post: A380Lover
  [Press Release] Factsheet: Status of Construction of the Thomson-East Coast Line A380Lover 0 7,632 10 November 2017, 04:33 PM
Last Post: A380Lover
  [News Article] Design of S’pore’s oldest MRT lines not ideal and improvements will take time A380Lover 0 6,406 08 November 2017, 11:53 AM
Last Post: A380Lover
  [News Article] North-South, East-West lines will ‘likely’ see shortened operating hours on weekdays: C151 - 061/062 0 6,365 08 November 2017, 08:23 AM
Last Post: C151 - 061/062
  [News Article] Thomson-East Coast Line could be extended to connect to Changi Airport A380Lover 7 5,404 29 April 2017, 09:49 AM
Last Post: xavier2002
  [News Article] Changi's T5 likely to be served by 2 MRT lines A380Lover 0 5,347 17 March 2017, 08:24 PM
Last Post: A380Lover
  [News Article] Changi's T5 likely to be served by 2 MRT lines A380Lover 0 4,984 06 March 2017, 07:30 PM
Last Post: A380Lover
  [News Article] Track circuit faults unrelated to sleeper replacement works: SMRT A380Lover 0 5,016 05 February 2017, 07:36 PM
Last Post: A380Lover
  [Press Release] Limited Tender for Thomson-East Coast Line Operator Licence in 1Q2017 A380Lover 0 1,528 05 November 2016, 11:27 AM
Last Post: A380Lover

Forum Jump:


Users browsing this thread: 1 Guest(s)