End-of-Life Upgrade for Kawasaki Heavy Industries C151
#1
NOTE: Please refer to Page 1 of this thread for more information


Kawasaki Heavy Industries C151 End-Of-Life Upgrade
1. Fully Upgraded
2. Propulsion Upgraded/Changed-Out
3. Suspect Under Upgrading/Change-Out (MIA)
4. Not Upgraded/Changed-Out

1. Fully Upgraded (0/66)

-CANCELLED-

2. Propulsion Upgraded/Changed-Out (6/66) 

025/026 (LIVE as of 06/07/17)
055/056 (LIVE as of 30/07/15)
065/066 (LIVE as of 08/03/17) 
095/096 (LIVE as of 15/08/17)
109/110 (LIVE as of 27/04/17)
131/132 (LIVE as of 30/07/15)


3. Suspect Under Upgrading/Change-Out (MIA) (0/66)



4. Not Upgraded/Changed-Out (60/66)

001/002
003/004
005/006
007/008
009/010
011/012
013/014
015/016
017/018
019/020
021/022
023/024
027/028
029/030
031/032
033/034
035/036
037/038
039/040
041/042
043/044
045/046
047/048
049/050
051/052
053/054
057/058
059/060
061/062
063/064
067/068
069/070
071/072
073/074
075/076
077/078
079/080
081/082
083/084
085/086
087/088
089/090
091/092
093/094
097/098
099/100
101/102
103/104
105/106
107/108
111/112
113/114
115/116
117/118
119/120
121/122
123/124
125/126
127/128
129/130


List in Order (Chronological order - PMSM)
Jun 2015: 131/132
Jul 2015: 055/056
Mar 2017: 065/066
Apr 2017: 109/110
Jul 2017: 025/026
Aug 2017: 095/096

Total No. of PMSM upgraded KHI trains: 6

Last Updated: 150817

Administrator Notice:
Since the PMSM trial would start next year, its about time the discussion as well as the monitoring of progress should start. Have any suspected trains? post it here Smile 

Note: Only 2 KHI trains will trial the new propulsion

NOTE: Currently, LTA has put the project on hold

UPDATE as of 311016: LTA has decided to cancel the EOL upgrading project and retire the KHI C151s. 

UPDATE as of 010117: LTA has decided to still proceed on with some trains.

Benjamin Goh 
Forum Administrator (ORD LOH!)
SGTrains.com
Youtube | Foursquare 
Anime | Aviation | Bus | Train | Photography


今日も JR西日本をご利用くださいましてありがとうございます。この電車は環状線内回り、大阪、西九条、弁天町方面行きです。次は、桜ノ宮に泊まります。お客様にお願い致します、有線座席ではお年寄りや体の不自由なお客様、妊娠中や乳幼児をお連れのお客様がいらっしゃいましたら席をお譲り下さい。ご協力をお願いします。
Reply
#2
I think 1 C651 can go for both PMSM, refurbishing and new signalling system, which will drag 3 months.
Reply
#3
Wait. SIE will also get the same change out?

I thought the refurbishment tender was won by Siemens? Huh
Reply
#4
Hii, to clarify, Siemens won the tender to refurbish the trains which only includes the interior and exterior. The traction or propulsion is not included in the tender. Similar to the KHI one when the tender to refurb was awarded

[Edit]: I'll clarify and get back
Benjamin Goh 
Forum Administrator (ORD LOH!)
SGTrains.com
Youtube | Foursquare 
Anime | Aviation | Bus | Train | Photography


今日も JR西日本をご利用くださいましてありがとうございます。この電車は環状線内回り、大阪、西九条、弁天町方面行きです。次は、桜ノ宮に泊まります。お客様にお願い致します、有線座席ではお年寄りや体の不自由なお客様、妊娠中や乳幼児をお連れのお客様がいらっしゃいましたら席をお譲り下さい。ご協力をお願いします。
[-] The following 1 user Likes nakanoben's post:
  • habiTAT
Reply
#5
Hey there! I am not so sure what is propulsion upgrading/change-out. Could you let me know more about it? If there is any link to it, can you just share it over here? I would appreciate your help. Thanks!
Reply
#6
(31 October 2014, 07:01 PM)masterchief Wrote:   Show/Hide

I think it's the replacement of the the engine.
Reply
#7
Propulsion upgrade/change out involves the removal of the current motor engine and installing a new one.

Hence, the rolling stock's accel/deaccel sound is going to change in future.
[-] The following 1 user Likes Ethan777's post:
  • habiTAT
Reply
#8
Two train sets go for the trial, according to this article:
http://response.jp/article/2013/07/04/201501.html
Reply
#9
(30 October 2014, 10:25 PM)habiTAT Wrote:   Show/Hide

Toshiba has been awarded the tender to change the propulsion for KHI and SIE, as far as I am aware of. Big Grin

(05 July 2013, 12:26 PM)SBS6019J Wrote:   Show/Hide
[Image: finalsignature2.jpg]
Reply
#10
I think its a little confusing so let me break it down for you.

SMRT has awarded the Refurbishment, changeout of propulsion and testing/commissioning to the contractor SRE

SRE in turn tendered Siemens for the refurbishment of the interior only

While (I m not confirmed, but I think Toshiba is doing the PMSM for SIE)

So SRE job is to manage the project
Benjamin Goh 
Forum Administrator (ORD LOH!)
SGTrains.com
Youtube | Foursquare 
Anime | Aviation | Bus | Train | Photography


今日も JR西日本をご利用くださいましてありがとうございます。この電車は環状線内回り、大阪、西九条、弁天町方面行きです。次は、桜ノ宮に泊まります。お客様にお願い致します、有線座席ではお年寄りや体の不自由なお客様、妊娠中や乳幼児をお連れのお客様がいらっしゃいましたら席をお譲り下さい。ご協力をお願いします。
[-] The following 3 users Like nakanoben's post:
  • A380Lover, habiTAT, SBS8300H
Reply


Possibly Related Threads...
Thread Author Replies Views Last Post
  Kawasaki Heavy Industries-CSR Sifang C151A Repairs (KSF) joelong243w 1,313 1,231,299 18 April 2019, 05:47 PM
Last Post: A380Lover
  Delivery of Kawasaki-CRRC Sifang C151C nakanoben 175 84,089 23 March 2019, 12:04 PM
Last Post: saffie730
  Delivery of Kawasaki-CRRC Sifang CT251 nakanoben 95 73,444 31 January 2019, 03:43 PM
Last Post: A380Lover
  EIS of Kawasaki Heavy Industries-CSR Sifang C151B nakanoben 332 234,388 22 May 2018, 01:29 PM
Last Post: Flip
  Delivery of Mitsubishi Heavy Industries Crystal Mover (C810A) nakanoben 35 16,677 02 August 2016, 05:10 PM
Last Post: smrtrainlovur
Information C151 & C751A High Capacity Modification (2015) nakanoben 66 24,963 15 December 2015, 12:49 PM
Last Post: smrtrainlovur